26/03/2023
Lack of provision during works – Firepool as an example
During the works on the new access into Firepool off Trenchard Way in 2023, a long section of Trenchard Way was operating with shuttle traffic signals. A length of the shared footway on the south side of Trenchard Way was rubble, there was no provision for cycling and no information on how cyclists were supposed to get through the area. We have tried riding with the traffic several times. On one occasion, traffic was coming towards us in the narrow section before we were able to ride through, with a huge amount of impatient traffic behind us. The signal timings didn’t allow sufficient time for cyclists to clear the section affected. When we got to the end, we were pretty desperate to rejoin the shared footway, but Somerset County Council (SCC) had made no provision to do that, so we were stuck on the carriageway.
Our recommendation to the council
We sent a sketch proposal to Somerset County Council (SCC) asking that cyclists be allowed to use the footway on a temporary basis with priority to pedestrians, utilising the crossings at each end of the works. This was based on observing what most people seem to be doing, without problem.
Somerset County Council replied as follows: “We have worked closely with the contractor to consider all temporary traffic management options, regrettably due to the lack of available width and the need to balance the needs of all users, it is not possible in this instance to safely accommodate cyclists through the temporary layout. Cyclists are therefore advised to dismount at either end of the works and follow the pedestrian route along the north side.”
In our response, we pointed out that it would take several minutes to walk along the footway, a significant time penalty and an unpleasant experience. Not surprisingly most cyclists cycled on the footway. The combined flows are low so we asked SCC again to formalise this on a temporary basis, with priority for pedestrians. SCC was not willing to cooperate.
A member of the public commented: “Somerset County Council make bold claims that they are encouraging Active Transport. This project is another example where cyclists have not even been considered as an afterthought before closing part of Trenchard Way Cycle path. There was no advance or current signage posted warning of the closure, nor has any reasonable provision been made to encourage cyclists to continue using the route during the necessary works. Not encouraging Active Transport! We also have no idea how long the closure will be, and more importantly, the Council plans for the ‘lost’ part of the cycle path after the completed work. These issues could easily be avoided if the Council and their contractors engaged with TACC and cyclists.”